Hailuoto fixed link: a causeway and two bridges

The link replacing the ferry from Riutunkari in Oulu to Hailuoto opened to traffic in June 2026, ahead of schedule.

In brief

For decades, Hailuoto was reached by ferry. Now the drive from the mainland to the island takes about eight minutes, and the link is open around the clock.

GRK built the link as part of an alliance with the client, the Finnish Transport Infrastructure Agency, and the designers AFRY and A-Insinöörit. The link consists of a causeway across the sea and the Riutta and Huikku bridges.

The work was done on open sea in wind and ice, with the water level varying. Construction started in May 2024 and progressed as planned from start to finish.

The project in figures

8.4

km

fixed link from the mainland to the island

767

m

deck of the Huikku bridge, the longer of the two

20,000

m³

of concrete in the project’s structures

8

min

by car, where the ferry timetable once ruled

This is not the achievement of a single organisation – instead, it is the shared success of the entire alliance.

Timo Takala · Project Manager, GRK

What made the project demanding

Open sea

Strong winds, ice conditions, large variations in water level and demanding marine logistics throughout construction.

Winter on site

In January 2025, the temperature on site ranged from 25 degrees below zero to above freezing. In thaw weather the sea rose and the wind made the work harder.

Large bridge pours

Continuous pours lasting several days. The deck of the Riutta bridge was the largest bridge pour ever made in Finland.

How the link was built

05/2024

Construction starts from Riutunkari

The causeway began to grow from the mainland shore towards the island. In the first year, about 5.5 kilometres of embankment were built across the sea.

Aerial view of the causeway and the bridge formwork at sea
The site in December 2024

12/2024

The causeway reaches the Huikku work bridge

Site vehicles could now drive all the way from Oulunsalo to Hailuoto. Over 2 million tonnes of blasted rock and crushed stone went into the causeway.

Rock embankment and work bridge on the frozen sea
The rock embankment and the Huikku work bridge, 20.12.2024

2025

The Riutta bridge

Piling was finished in January, and the bridge deck was cast in spring: the largest bridge pour ever made in Finland.

04/2026

The Huikku bridge deck

The deck of the longer bridge, 767 metres long and 10.2 metres wide, was cast in two shifts over three to four days. Over a hundred people took part.

Concrete pumps casting the Huikku bridge deck, workers on the reinforced deck
Casting the Huikku bridge deck, 13.4.2026

06/2026

The link opens to traffic

The link was opened ahead of schedule, without compromising on safety or quality.

The finished Hailuoto fixed link
The finished link