
Hailuoto fixed link: a causeway and two bridges
The link replacing the ferry from Riutunkari in Oulu to Hailuoto opened to traffic in June 2026, ahead of schedule.
In brief
For decades, Hailuoto was reached by ferry. Now the drive from the mainland to the island takes about eight minutes, and the link is open around the clock.
GRK built the link as part of an alliance with the client, the Finnish Transport Infrastructure Agency, and the designers AFRY and A-Insinöörit. The link consists of a causeway across the sea and the Riutta and Huikku bridges.
The work was done on open sea in wind and ice, with the water level varying. Construction started in May 2024 and progressed as planned from start to finish.
The project in figures
8.4
km
fixed link from the mainland to the island
767
m
deck of the Huikku bridge, the longer of the two
20,000
m³
of concrete in the project’s structures
8
min
by car, where the ferry timetable once ruled
This is not the achievement of a single organisation – instead, it is the shared success of the entire alliance.
Timo Takala · Project Manager, GRK
What made the project demanding
Open sea
Strong winds, ice conditions, large variations in water level and demanding marine logistics throughout construction.
Winter on site
In January 2025, the temperature on site ranged from 25 degrees below zero to above freezing. In thaw weather the sea rose and the wind made the work harder.
Large bridge pours
Continuous pours lasting several days. The deck of the Riutta bridge was the largest bridge pour ever made in Finland.
How the link was built
05/2024
Construction starts from Riutunkari
The causeway began to grow from the mainland shore towards the island. In the first year, about 5.5 kilometres of embankment were built across the sea.

12/2024
The causeway reaches the Huikku work bridge
Site vehicles could now drive all the way from Oulunsalo to Hailuoto. Over 2 million tonnes of blasted rock and crushed stone went into the causeway.

2025
The Riutta bridge
Piling was finished in January, and the bridge deck was cast in spring: the largest bridge pour ever made in Finland.
04/2026
The Huikku bridge deck
The deck of the longer bridge, 767 metres long and 10.2 metres wide, was cast in two shifts over three to four days. Over a hundred people took part.

06/2026
The link opens to traffic
The link was opened ahead of schedule, without compromising on safety or quality.

A similar project in planning?
Tell us about the project, and we assess how it could be delivered. A half-finished design is fine.
-
Jaakko Mäkelä
Business Director, Civil Engineering and Paving